Build an AI data center

Build an AI Data Center in 15 Months With a Prefab Design

A site-ready design for a liquid-cooled AI hall, built from prefab modules made off-site while the ground is prepared, so the schedule runs in parallel. Pair it with land and power from our site portfolio, or with land you already control.

Engineer with a laptop walking a data center server aisle

Prefab AI data center, Phase I

  • 26MW power, 20MW IT
  • 120kW liquid-cooled racks
  • About 1.3 design PUE, Tier III
  • 15 months to commission

Plan Your Build

Send the site or region, MW and target date. We reply with a design fit, partners and a schedule.

The Design

A concept design for an AI campus for neoclouds on industrial land in Texas, built as a prefab modular steel structure. Phase II adds a second building on the same plot.

Fiber patch cords at a high-density patch panel
Phase I power
26MW capacity, 20MW IT load
Racks
288 in 4 data halls: 168 AI racks at 120kW, 48 network and storage racks at 17kW, 72 spare
Cooling
Liquid cooling through CDUs plus air-cooled chilled water, under 20 gpm of water
Power
Dual 24.9kV incoming lines stepped down to 415V, 2N backup generation and 2N UPS at rack level
Fabric
Racks within 100m of each other for the NVIDIA InfiniBand fabric
Floor area
29,550 m² in Phase I, 12,434 m² in Phase II
Rating
About 1.3 design PUE, Uptime Tier III

This is a design package, not a powered site. Land, the utility contract and the power price are set for each client.

How 15 Months Works

Modules are designed and built off-site while US contractors prepare the ground, so the two run at the same time instead of one after the other.

General Contractor

Coordination, cost control, quality and handover across the whole program.

Design and Consultancy

Diligence, design and permits.

Prefab Modules

Modules, mechanical and electrical systems, integration and shipping.

On-Site Construction

Groundworks by local US subcontractors, then module assembly.

Commissioning

Verification and testing before go-live.

Fiber and Optics

Trunks, cabling and transceivers from Vocom on one order, delivered to site.

Data center fiber →

The Build Path in Ten Phases

A conventional build takes 2 to 4 years. Phases 2 to 4 usually run in parallel, because power and permits set the critical path. The highlighted phases carry the longest lead times.

  1. 01Strategy and business case2 to 4 mo
  2. 02Site selection and control3 to 9 mo
  3. 03Power strategy12 to 60 mo
  4. 04Permitting6 to 18 mo
  5. 05Financing3 to 9 mo
  6. 06Design4 to 9 mo
  7. 07Procurement12 to 24 mo lead
  8. 08Construction12 to 24 mo
  9. 09Commissioning2 to 4 mo
  10. 10Go-live and operationsOngoing

Secure power before spending on land or design. Sites without a credible grid date are the most common cause of failed projects.

Power-First Sites to Build On

Land with power, or a firm date for it. The full site list has the rest.

Texas

50MW

Pairs with the prefab design above.

New Mexico

25MW, Solar

The lowest power cost in the portfolio, suited to cost-sensitive, large-scale compute.

Kyushu, Japan

1GW, Phased

Nuclear and thermal power, built in three phases of 100MW, 250MW and 650MW, so capital goes in stages.

Batam, Indonesia

500MW

A digital park a short ferry ride from Singapore, with a dedicated power plant under construction and grid interconnection planned for 2027. The plant is coal-fired, with solar planned later. Subsea fiber reaches Singapore in under 11ms.

Johor Bahru, Malaysia

300MW

Full 300MW available, across the causeway from Singapore.

Hokkaido, Japan

1.2GW

The largest single site in the portfolio.

Inside an AI Data Center

Frequently Asked Questions

Why build with prefab modules?

The modules are made off-site while the ground is prepared, so the two run in parallel. The plan runs about 15 months from design to commissioning, against 24 to 48 months for a typical conventional build.

What does it cost to build an AI data center?

Industry figures put a build at roughly $9M to $15M per MW before IT equipment. The design package and partners are priced per project.

Do I have to use one of your sites?

No. The design pairs with any site in our portfolio or land you already control, as long as the power date is credible.

Can Vocom supply what goes inside?

Yes. Vocom supplies the fiber cabling, optical transceivers and Supermicro AI servers for the halls, on one order delivered to site.

Capacity, power and timing figures are provided by the site owners and are verified in diligence. Documents, pricing and exact locations go to qualified buyers under NDA.